Mud Pumps and High-Pressure Iron

Drilling Equipment Inspections

How often
Mud pumps and high-pressure piping: Category I daily, II weekly, III annual. Pulsation dampeners: I daily, II weekly. Pump relief valves: shear pins pulled and the valve blown down every rig move or monthly, full disassembly quarterly, Category III annual. 2 in. 1502 hardline: annual inspection and charted 250 / 5,000 psi test.
Source: Nordic PM Plan 9.0 Table 6 and Table 3 (notes ** and quarterly note); Nordic PM Plan Appendix B 11.1 and 11.6
📋 Inspection Information
📏 Readings
✅ Checklist

Answer every line. N/A means it does not apply today. Every Fail needs a note saying what is wrong.

Rigmaster mud pumps
Pulsation dampener pre-charge checked (Rig 4 Start-Up lists 100 to 300 psi; follow the dampener nameplate if it differs)
Source: Nordic R4 Rig Start-Up 7.0 steps 5 and 9
Fluid end: no washouts or leaks at covers, liners, packing or valves
Source: Nordic PM Plan 9.0 (Category II: fluid leaks)
Guards on belts, chains and drives in place
Source: API RP 54 (4th ed.) 6.3.2, 6.3.3
Accumulated pumping hours documented today
Source: Nordic PM Plan Appendix B 11.1 (Rig 4)
Mud pump discharge gauges calibrated within 3 years
Source: Nordic PM Plan Appendix B 11.9
Centrifugal charge pump motor securely mounted, wired and bonded
Source: Nordic R4 Rig Start-Up 7.0 step 8; API RP 54 (4th ed.) 7.12.8
Pump relief valves
Correct shear pin installed (O'Drill MCM pins for the OTECO valve)
Source: Nordic PM Plan 9.0 (Category III, mud pump relief valve); API RP 54 (4th ed.) 7.11.9
Set at or below the rated working pressure of the pump and the piping it protects
Source: API RP 54 (4th ed.) 7.11.6
Stem and shear pin enclosed; cover cannot come loose
Source: API RP 54 (4th ed.) 7.11.9
Discharge piping full size, unobstructed, routed to the circulating system and secured
Source: API RP 54 (4th ed.) 7.11.2, 7.11.7, 7.11.8
Pins pulled, stem hand-functioned and the valve blown down through the pump discharge this month or this rig move, with new pins installed
Source: Nordic PM Plan 9.0 Table 3 note **
High-pressure iron and hoses
Every hardline component banded and identified; annual inspection current
Source: Nordic PM Plan Appendix B 11.6
Hammer unions made up of like halves (same pressure rating and thread); Go/No-Go rings used wherever 602 and 1502 could be mixed
Source: API RP 54 (4th ed.) 7.11.5; API RP 7HU1
2 in. 1502 unions from the approved makers (SPM, FMC, Kemper, WECO, ABCO, Anson); MSI, Savage or Cameron replaced when taken out of service
Source: Nordic PM Plan Appendix B 11.6
Chicksan swivels rotate freely by hand
Source: Nordic PM Plan Appendix B 11.6
No rig-made high-pressure hoses in service unless the Rig Manager authorized one for an emergency
Source: Nordic PM Plan Appendix B 11.5
Lines and hoses secured against whip per the risk assessment
Source: API RP 54 (4th ed.) 7.11.3
Nothing run above its rated working pressure
Source: API RP 54 (4th ed.) 7.11.4